Hi, expert
I was confused with the logic about ML actual cost component split. the notes said it should be the same as cost component structure in planning.
I created a new materail, and made cost estimate for it, then post the price with ck24.
Bute I found difference exist between cost estimate result (CK13N )and the S price ACCS result( MLCCSPD), why this happens? Can anyone give some guides?