Hi All,
We have a mtce plan running on a mtce strategy with 12 months cycle (mtce package), business required the mtce cycle to be changed to 24 months.
So a new mtce package of 24 months was created (in existing strategy) and task list was updated to new mtce package.
The issue is with 2nd planned date, we expected the 2nd planned date to be 01.01.2018 and not 01.01.2017
Mtce Package | Planned Date | Completion date | Remark | |
Start of cycle | 01.01.2015 | |||
12 Months | 1st Planned Date | 01.01.2016 | 01.01.2016 | |
Strategy changed from 12 Months to 24 Months | ||||
24 Months package | 2nd Planned Date | 01.01.2017 | The 2nd planned date should be 01.01.2018 based on completion date instead of 01.01.2017 |
Note : Mtce plans have 'Completion Requirement' checked.There are 5000 mtce plans that reqired the change, so we dont want to delete/skip the call and generate a new call. We want IP30 to take bring up a correct date.Tried using IP11U but does not help.
Any help would be appriciated.
Regards
Arif